Action Date | Action Description |
---|---|
Mar 24, 2006 | Assent Application Received |
Mar 27, 2006 | Administrative Review for Completeness |
Mar 29, 2006 | Deficient Application - Owner Notification Sent |
Apr 06, 2006 | Deficient Application Picked Up |
Jul 31, 2006 | Deficiency Response Received |
Aug 18, 2006 | Team Review for Completeness |
Aug 18, 2006 | Application Accepted |
Aug 21, 2006 | 30 day Public Notice Issued |
Sep 21, 2006 | Public Notice End Date |
Sep 28, 2006 | Typist for Processing |
Sep 28, 2006 | Executive Sign Off |
Sep 28, 2006 | Sent to Photo Copy |
Sep 28, 2006 | Permit Approved |
Sep 28, 2006 | Biologist Report |
Sep 28, 2006 | Engineering Report |
Oct 12, 2006 | Land Evidence Date |
Oct 16, 2006 | US Army Corp of Engineers Permit Date |
Oct 19, 2006 | US Army Corps of Engineers Approval Received |
Oct 20, 2006 | Water Quality Certification |
Nov 21, 2006 | Commencement of Work Notice received |