Action Date | Action Description |
---|---|
Sep 20, 2007 | Assent Application Received |
Sep 21, 2007 | Administrative Review for Completeness |
Sep 24, 2007 | Team Review for Completeness |
Sep 24, 2007 | Team Review for Completeness |
Sep 24, 2007 | Application Accepted |
Sep 26, 2007 | 30 day Public Notice Issued |
Oct 04, 2007 | HPHC Historical Preservation No Effect |
Oct 26, 2007 | Public Notice End Date |
Oct 29, 2007 | US Army Corp of Engineers Permit Date |
Nov 07, 2007 | US Army Corps of Engineers Approval Received |
Nov 20, 2007 | Typist for Processing |
Nov 20, 2007 | Biologist Report |
Nov 20, 2007 | Engineering Report |
Nov 20, 2007 | Dock Meeting -- Approval |
Nov 21, 2007 | Executive Sign Off |
Nov 21, 2007 | Sent to Photo Copy |
Nov 21, 2007 | Permit Approved |
Dec 19, 2007 | Land Evidence Date |
Jul 06, 2011 | Commencement of Work Notice received |
Jul 06, 2011 | Extension of Permit Request |
Jul 11, 2011 | Extension Toll letter mailed |