Action Date | Action Description |
---|---|
Oct 26, 2011 | Assent Application Received |
Oct 31, 2011 | Administrative Review for Completeness |
Nov 01, 2011 | Team Review for Completeness |
Nov 01, 2011 | Application Accepted |
Nov 28, 2011 | 30 day Public Notice Issued |
Dec 12, 2011 | HPHC Historical Preservation No Effect |
Dec 28, 2011 | Public Notice End Date |
Jan 10, 2012 | Biologist Report |
Jan 17, 2012 | Typist for Processing |
Jan 17, 2012 | Category A* (Docks) |
Jan 17, 2012 | Permit Approved |
Jan 18, 2012 | Executive Sign Off |
Jan 18, 2012 | Sent to Photo Copy |
Feb 03, 2012 | Land Evidence Date |
Mar 19, 2012 | US Army Corps of Engineers Approval Received |