Action Date | Action Description |
---|---|
Feb 20, 2012 | Assent Application Received |
Feb 20, 2012 | Administrative Review for Completeness |
Feb 21, 2012 | Team Review for Completeness |
Feb 21, 2012 | Application Accepted |
Feb 28, 2012 | HPHC Historical Preservation No Effect |
Mar 12, 2012 | Geologist Report |
Mar 13, 2012 | Typist for Processing |
Mar 13, 2012 | Permit Approved |
Mar 13, 2012 | Pre-construction requirement by CRMC staff |
Mar 14, 2012 | Executive Sign Off |
Mar 14, 2012 | Sent to Photo Copy |