Action Date | Action Description |
---|---|
Feb 18, 2013 | Assent Application Received |
Feb 18, 2013 | Administrative Review for Completeness |
Feb 19, 2013 | Team Review for Completeness |
Feb 19, 2013 | Team Review for Completeness |
Feb 19, 2013 | Application Accepted |
Mar 05, 2013 | 30 day Public Notice Issued |
May 06, 2013 | HPHC Historical Preservation No Effect |
Jun 05, 2013 | Water Quality Certification |
Jun 12, 2013 | US Army Corps of Engineers Approval Received |
Jun 14, 2013 | Mail Agenda Notice |
Jun 14, 2013 | Engineering Report |
Jun 25, 2013 | Semi-Monthly Meeting Held |
Jun 25, 2013 | Council Approval Granted |
Jun 25, 2013 | Semi-Monthly Meeting Date Scheduled |
Jul 31, 2013 | Under Review/Decision |
Jul 31, 2013 | Legal Response/Decision |
Aug 05, 2013 | Stipulation Package from Biologist |
Aug 05, 2013 | Stipulation Package by Engineer |
Aug 05, 2013 | Biologist Report |
Aug 13, 2013 | 30 Day Appeal Notification to Owner |
Aug 15, 2013 | Permit Approved |
Aug 15, 2013 | Typist for Processing |
Aug 19, 2013 | Executive Sign Off |
Aug 19, 2013 | Sent to Photo Copy |