Action Date | Action Description |
---|---|
Apr 23, 2013 | Assent Application Received |
Apr 23, 2013 | Administrative Review for Completeness |
Apr 30, 2013 | Team Review for Completeness |
Apr 30, 2013 | Team Review for Completeness |
Apr 30, 2013 | Application Accepted |
May 10, 2013 | HPHC Historical Preservation No Effect |
Jun 03, 2013 | Policy Review |
Jun 04, 2013 | Typist for Processing |
Jun 04, 2013 | Permit Approved |
Jun 07, 2013 | Executive Sign Off |
Jun 07, 2013 | Sent to Photo Copy |
Jul 12, 2013 | US Army Corps of Engineers Approval Received |
Sep 09, 2013 | Commencement of Work Notice received |
Mar 28, 2014 | Modification Request |
Mar 31, 2014 | Administrative Review for Completeness |
Apr 04, 2014 | Team Review for Completeness |
Apr 07, 2014 | Policy Review |
Apr 11, 2014 | Typist for Processing |
Apr 11, 2014 | Modification Approved |
Apr 14, 2014 | Executive Sign Off |
Apr 14, 2014 | Sent to Photo Copy |
May 15, 2014 | Land Evidence Date |