Action Date | Action Description |
---|---|
Aug 15, 2011 | Assent Application Received |
Aug 16, 2011 | Administrative Review for Completeness |
Aug 16, 2011 | Team Review for Completeness |
Aug 16, 2011 | Team Review for Completeness |
Aug 17, 2011 | Application Accepted |
Aug 18, 2011 | Biologist Report |
Aug 18, 2011 | Engineering Report |
Aug 26, 2011 | Typist for Processing |
Aug 26, 2011 | Executive Sign Off |
Aug 26, 2011 | Sent to Photo Copy |
Aug 26, 2011 | Permit Approved |
Sep 07, 2011 | HPHC Historical Preservation No Effect |
Jul 10, 2013 | Typist for Processing |
Jul 10, 2013 | Assent Correction Mailed |
Jul 11, 2013 | Executive Sign Off |
Jul 11, 2013 | Sent to Photo Copy |