Action Date | Action Description |
---|---|
Biologist Report | |
Engineering Report | |
Jul 22, 2024 | Maintenance Certification Request |
Jul 24, 2024 | Administrative Review for Completeness |
Aug 08, 2024 | Eng Team Review for Completeness |
Aug 08, 2024 | Deficient Application - Owner Notification Sent |
Aug 14, 2024 | Deficient Application Picked Up |
Oct 16, 2024 | Deficiency Response Received |
Oct 23, 2024 | Bio Team Review for Completeness |
Oct 23, 2024 | Eng Team Review for Completeness |
Oct 23, 2024 | Application Accepted |
Oct 23, 2024 | Project Manager |
Oct 24, 2024 | Additional Information Received |
Oct 30, 2024 | HPHC Historical Preservation No Effect |
Nov 27, 2024 | Plans Received |