Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Oct 05, 2022 | Assent Application Received |
Oct 07, 2022 | Administrative Review for Completeness |
Oct 07, 2022 | Bio Team Review for Completeness |
Oct 07, 2022 | Project Manager |
Oct 07, 2022 | Application Accepted |
Oct 07, 2022 | Category A* (Docks) |
Oct 18, 2022 | HPHC Historical Preservation No Effect |
Oct 24, 2022 | 30 day Public Notice Issued |
Nov 21, 2022 | Objections/Comments Received |
Nov 23, 2022 | Correspondence Mailed/Faxed/E-mailed |
Nov 23, 2022 | Additional Information Requested from Applicant |
Nov 24, 2022 | Public Notice End Date |
Nov 28, 2022 | Letter of Support for Project |
Jan 20, 2023 | Biologist Report |
Jan 26, 2023 | Supervisor Biologist SignOff |
Jan 26, 2023 | Supervisor Engineer SignOff |
Jan 26, 2023 | Executive Signoff of Staff Reports |
Jun 14, 2023 | Ready to Schedule Semi-Monthly Meeting |
Jun 14, 2023 | Mail Agenda Notice |
Jun 22, 2023 | Objections/Comments Received |
Jun 27, 2023 | Council Approval Granted |
Jun 27, 2023 | Semi-Monthly Meeting Date Scheduled |
Feb 02, 2024 | Note to File |
Jun 18, 2024 | Correspondence Received |
Jun 18, 2024 | Legal Response/Decision |
Nov 06, 2024 | Permit Approved |
Nov 06, 2024 | Permit Mailed |
Nov 06, 2024 | Stipulation Package from Biologist |
Nov 22, 2024 | Commencement of Work Notice received |
Nov 22, 2024 | Land Evidence Date |