Action Date | Action Description |
---|---|
Land Evidence Date | |
Dock Post-Construction Certification by Engineer received. | |
Feb 05, 2024 | Assent Application Received |
Feb 09, 2024 | Administrative Review for Completeness |
Apr 18, 2024 | Bio Team Review for Completeness |
Apr 18, 2024 | Application Accepted |
Apr 18, 2024 | Project Manager |
Apr 18, 2024 | Category A* (Docks) |
May 07, 2024 | HPHC Historical Preservation No Effect |
Jul 10, 2024 | Plans Received |
Nov 12, 2024 | Additional Information Received |
Nov 29, 2024 | 30 day Public Notice Issued |
Dec 29, 2024 | Public Notice End Date |
Mar 03, 2025 | Biologist Report |
Mar 05, 2025 | Typist for Processing |
Mar 05, 2025 | Executive Sign Off |
Mar 05, 2025 | Sent to Photo Copy |
Mar 05, 2025 | Permit Approved |
Mar 10, 2025 | Permit Mailed |