Action Date | Action Description |
---|---|
Monitoring Report | |
Jul 26, 2024 | Assent Application Received |
Jul 31, 2024 | Administrative Review for Completeness |
Aug 01, 2024 | Bio Team Review for Completeness |
Aug 01, 2024 | Project Manager |
Aug 01, 2024 | Application Accepted |
Aug 26, 2024 | HPHC Historical Preservation No Effect |
Nov 13, 2024 | Additional Information Requested from Applicant |
Feb 04, 2025 | Additional Information Received |
Feb 12, 2025 | Biologist Report |
Feb 17, 2025 | Typist for Processing |
Feb 17, 2025 | Executive Sign Off |
Feb 17, 2025 | Sent to Photo Copy |
Feb 17, 2025 | Permit Approved |
Feb 18, 2025 | Permit Mailed |
Mar 06, 2025 | Land Evidence Date |