Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Aug 07, 2024 | Assent Application Received |
Aug 13, 2024 | Administrative Review for Completeness |
Aug 15, 2024 | Bio Team Review for Completeness |
Aug 15, 2024 | Application Accepted |
Aug 15, 2024 | Project Manager |
Aug 30, 2024 | HPHC Historical Preservation No Effect |
Sep 18, 2024 | 30 day Public Notice Issued |
Oct 18, 2024 | Public Notice End Date |
Dec 20, 2024 | Dock Meeting -- Approval |
Dec 31, 2024 | Biologist Report |
Jan 03, 2025 | Permit Mailed |
Jan 03, 2025 | Typist for Processing |
Jan 03, 2025 | Executive Sign Off |
Jan 03, 2025 | Sent to Photo Copy |
Jan 03, 2025 | Permit Approved |
Jan 16, 2025 | Land Evidence Date |