Action Date | Action Description |
---|---|
Assent Requirement | |
Aug 23, 2024 | Assent Application Received |
Aug 30, 2024 | Administrative Review for Completeness |
Sep 10, 2024 | Bio Team Review for Completeness |
Sep 10, 2024 | Deficient Application - Owner Notification Sent |
Sep 23, 2024 | Deficiency Response Received |
Sep 23, 2024 | Bio Team Review for Completeness |
Sep 30, 2024 | Application Accepted |
Sep 30, 2024 | Project Manager |
Oct 10, 2024 | HPHC Historical Preservation No Effect |
Oct 16, 2024 | Biologist Report |
Nov 11, 2024 | Geologist Report |
Jan 07, 2025 | Typist for Processing |
Jan 07, 2025 | Executive Sign Off |
Jan 07, 2025 | Sent to Photo Copy |
Jan 07, 2025 | Permit Approved |
Jan 10, 2025 | Permit Mailed |