Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Land Evidence Date | |
Sep 25, 2024 | Assent Application Received |
Oct 01, 2024 | Administrative Review for Completeness |
Oct 18, 2024 | Bio Team Review for Completeness |
Oct 18, 2024 | Deficient Application - Owner Notification Sent |
Nov 25, 2024 | Deficiency Response Received |
Nov 27, 2024 | Bio Team Review for Completeness |
Nov 27, 2024 | Application Accepted |
Nov 27, 2024 | Project Manager |
Dec 02, 2024 | 30 day Public Notice Issued |
Dec 09, 2024 | HPHC Historical Preservation No Effect |
Jan 02, 2025 | Public Notice End Date |
Jan 29, 2025 | Dock/1.1.6 Review approval |
Jan 29, 2025 | Typist for Processing |
Jan 29, 2025 | Executive Sign Off |
Jan 29, 2025 | Sent to Photo Copy |
Jan 29, 2025 | Permit Approved |
Jan 29, 2025 | Biologist Report |
Jan 30, 2025 | Permit Mailed |
Feb 03, 2025 | Additional Information Received |