Action Date | Action Description |
---|---|
Land Evidence Date | |
Oct 10, 2024 | Assent Application Received |
Oct 18, 2024 | Administrative Review for Completeness |
Oct 21, 2024 | Eng Team Review for Completeness |
Oct 21, 2024 | Project Manager |
Oct 21, 2024 | Application Accepted |
Oct 28, 2024 | HPHC Historical Preservation No Effect |
Nov 26, 2024 | 30 day Public Notice Issued |
Dec 19, 2024 | Additional Information Requested from Applicant |
Dec 26, 2024 | Public Notice End Date |
Jan 03, 2025 | Plans Received |
Jan 07, 2025 | Engineering Report |
Jan 22, 2025 | Typist for Processing |
Jan 22, 2025 | Executive Sign Off |
Jan 22, 2025 | Sent to Photo Copy |
Jan 22, 2025 | Permit Approved |
Jan 24, 2025 | Permit Mailed |