Action Date | Action Description |
---|---|
Land Evidence Date | |
Oct 11, 2024 | Assent Application Received |
Oct 18, 2024 | Administrative Review for Completeness |
Oct 23, 2024 | Bio Team Review for Completeness |
Oct 25, 2024 | Deficient Application - Owner Notification Sent |
Dec 02, 2024 | Deficiency Response Received |
Dec 12, 2024 | Additional Information Requested from Applicant |
Dec 18, 2024 | Application Accepted |
Dec 18, 2024 | Project Manager |
Dec 18, 2024 | Bio Team Review for Completeness |
Jan 08, 2025 | HPHC Historical Preservation No Effect |
Feb 13, 2025 | Correspondence Received |
Feb 14, 2025 | Correspondence Mailed/Faxed/E-mailed |
Feb 21, 2025 | Typist for Processing |
Feb 21, 2025 | Executive Sign Off |
Feb 21, 2025 | Sent to Photo Copy |
Feb 21, 2025 | Permit Approved |
Feb 21, 2025 | Biologist Report |
Feb 25, 2025 | Permit Mailed |