Action Date | Action Description |
---|---|
Land Evidence Date | |
Oct 21, 2024 | Assent Application Received |
Oct 23, 2024 | Administrative Review for Completeness |
Oct 25, 2024 | Project Manager |
Oct 25, 2024 | Team Review for Completeness |
Oct 25, 2024 | Application Accepted |
Feb 11, 2025 | Geologist Report |
Feb 17, 2025 | Typist for Processing |
Feb 17, 2025 | Executive Sign Off |
Feb 17, 2025 | Sent to Photo Copy |
Feb 17, 2025 | Permit Approved |
Feb 18, 2025 | Permit Mailed |
Mar 07, 2025 | Correspondence Received |