Action Date | Action Description |
---|---|
Dec 17, 2024 | Assent Application Received |
Dec 18, 2024 | Administrative Review for Completeness |
Dec 20, 2024 | Bio Team Review for Completeness |
Dec 30, 2024 | Team Review for Completeness |
Dec 30, 2024 | Application Accepted |
Dec 30, 2024 | Project Manager |
Jan 06, 2025 | HPHC Historical Preservation Comments/Concerns |
Jan 07, 2025 | Additional Information Requested from Applicant |
Jan 07, 2025 | Additional Information Received |
Jan 13, 2025 | Plans Received |
Jan 27, 2025 | Geologist Report |
Jan 29, 2025 | Plans Received |
Jan 31, 2025 | HPHC Historical Preservation Comments/Concerns |
Feb 26, 2025 | HPHC No Objection |
Feb 26, 2025 | Typist for Processing |
Feb 26, 2025 | Executive Sign Off |
Feb 26, 2025 | Sent to Photo Copy |
Feb 26, 2025 | Permit Approved |
Feb 26, 2025 | Biologist Report |
Mar 03, 2025 | Permit Mailed |
Mar 05, 2025 | Commencement of Work Notice received |
Mar 05, 2025 | Land Evidence Date |