Action Date | Action Description |
---|---|
Dock Post-Construction Certification by Engineer received. | |
Dec 23, 2024 | Assent Application Received |
Dec 30, 2024 | Administrative Review for Completeness |
Dec 30, 2024 | Bio Team Review for Completeness |
Dec 30, 2024 | Project Manager |
Dec 30, 2024 | Application Accepted |
Jan 02, 2025 | HPHC Historical Preservation No Effect |
Jan 21, 2025 | 30 day Public Notice Issued |
Jan 29, 2025 | Dock Meeting -- Approval |
Feb 22, 2025 | Public Notice End Date |
Feb 28, 2025 | Biologist Report |
Mar 04, 2025 | Typist for Processing |
Mar 04, 2025 | Executive Sign Off |
Mar 04, 2025 | Sent to Photo Copy |
Mar 04, 2025 | Permit Approved |
Mar 06, 2025 | Permit Mailed |
Mar 10, 2025 | Land Evidence Date |