Action Date | Action Description |
---|---|
Land Evidence Date | |
Jan 31, 2025 | Assent Application Received |
Feb 07, 2025 | Administrative Review for Completeness |
Feb 11, 2025 | Bio Team Review for Completeness |
Feb 11, 2025 | Project Manager |
Feb 11, 2025 | Application Accepted |
Feb 14, 2025 | HPHC Historical Preservation No Effect |
Feb 28, 2025 | Biologist Report |
Mar 03, 2025 | CHA Worksheet received |
Mar 05, 2025 | Typist for Processing |
Mar 05, 2025 | Executive Sign Off |
Mar 05, 2025 | Sent to Photo Copy |
Mar 05, 2025 | Permit Approved |
Mar 10, 2025 | Permit Mailed |