Action Date | Action Description |
---|---|
Oct 01, 2024 | CHA Worksheet received |
Oct 01, 2024 | Assent Application Received |
Oct 02, 2024 | Administrative Review for Completeness |
Oct 04, 2024 | Bio Team Review for Completeness |
Oct 04, 2024 | Application Accepted |
Oct 04, 2024 | Project Manager |
Oct 28, 2024 | HPHC Historical Preservation No Effect |
Nov 14, 2024 | Additional Information Requested from Applicant |
Dec 11, 2024 | Additional Information Received |
Dec 31, 2024 | Plans Received |
Jan 03, 2025 | Biologist Report |
Jan 07, 2025 | Typist for Processing |
Jan 07, 2025 | Executive Sign Off |
Jan 07, 2025 | Sent to Photo Copy |
Jan 07, 2025 | Permit Approved |
Jan 10, 2025 | Permit Mailed |
Jan 23, 2025 | Land Evidence Date |