Action Date | Action Description |
---|---|
Dec 23, 2024 | Freshwater Wetlands Application - New - received |
Dec 27, 2024 | Administrative Review for Completeness |
Dec 31, 2024 | Bio Team Review for Completeness |
Dec 31, 2024 | Project Manager |
Dec 31, 2024 | Additional Information Received |
Dec 31, 2024 | Application Accepted |
Jan 14, 2025 | Biologist Report |
Jan 15, 2025 | Typist for Processing |
Jan 15, 2025 | Executive Sign Off |
Jan 15, 2025 | Sent to Photo Copy |
Jan 15, 2025 | Permit Approved |
Jan 22, 2025 | Permit Mailed |
Jan 24, 2025 | Commencement of Work Notice received |
Jan 24, 2025 | Land Evidence Date |