Action Date | Action Description |
---|---|
Land Evidence Date | |
Apr 09, 2021 | Assent Application Received |
Apr 13, 2021 | Administrative Review for Completeness |
Apr 13, 2021 | CHA Worksheet received |
Apr 16, 2021 | Bio Team Review for Completeness |
Apr 16, 2021 | Application Accepted |
Apr 17, 2021 | Project Manager |
Apr 30, 2021 | HPHC Historical Preservation No Effect |
Apr 30, 2021 | HPHC Review Pending |
Aug 17, 2021 | Plans Received |
Aug 23, 2021 | Additional Information Received |
Sep 01, 2021 | Additional Information Received |
Sep 01, 2021 | Additional Information Received |
Apr 07, 2022 | Plans Received |
Aug 12, 2022 | Additional Information Received |
Aug 19, 2022 | Biologist Report |
Aug 22, 2022 | Permit Mailed |
Aug 22, 2022 | Typist for Processing |
Aug 22, 2022 | Executive Sign Off |
Aug 22, 2022 | Sent to Photo Copy |
Aug 22, 2022 | Permit Approved |
Sep 09, 2022 | Land Evidence Date |
Jan 10, 2025 | Modification Request |
Jan 22, 2025 | Administrative Review for Completeness |
Jan 22, 2025 | Bio Team Review for Completeness |
Jan 22, 2025 | Project Manager |
Jan 22, 2025 | Application Accepted |
Jan 24, 2025 | HPHC Historical Preservation No Effect |
Feb 28, 2025 | Biologist Report |
Mar 04, 2025 | Typist for Processing |
Mar 04, 2025 | Executive Sign Off |
Mar 04, 2025 | Sent to Photo Copy |
Mar 04, 2025 | Modification Approved |
Mar 04, 2025 | Modification mailed |
Mar 06, 2025 | Permit Mailed |