Action Date | Action Description |
---|---|
Executive Sign Off | |
Sent to Photo Copy | |
Process Extension | |
Jul 23, 2021 | Assent Application Received |
Jul 26, 2021 | Administrative Review for Completeness |
Jul 26, 2021 | CHA Worksheet received |
Jul 27, 2021 | Bio Team Review for Completeness |
Jul 27, 2021 | Application Accepted |
Jul 28, 2021 | Project Manager |
Aug 20, 2021 | HPHC Historical Preservation No Effect |
Aug 20, 2021 | HPHC Review Pending |
Sep 07, 2021 | Additional Information Requested from Applicant |
Jan 12, 2022 | Plans Received |
Feb 18, 2022 | Biologist Report |
Feb 23, 2022 | Typist for Processing |
Feb 23, 2022 | Executive Sign Off |
Feb 23, 2022 | Sent to Photo Copy |
Feb 23, 2022 | Permit Approved |
Feb 28, 2022 | Permit Mailed |
Mar 16, 2022 | Land Evidence Date |
Jan 21, 2025 | Modification Request |
Jan 27, 2025 | Administrative Review for Completeness |
Jan 31, 2025 | Bio Team Review for Completeness |
Jan 31, 2025 | Project Manager |
Jan 31, 2025 | Application Accepted |
Feb 25, 2025 | HPHC Historical Preservation No Effect |
Feb 27, 2025 | Biologist Report |
Mar 04, 2025 | Typist for Processing |
Mar 04, 2025 | Note to File |
Mar 05, 2025 | Extension of Permit Request |
Mar 05, 2025 | Enforcement Compliance Inspection Required |