Action Date | Action Description |
---|---|
Land Evidence Date | |
Jan 17, 2025 | Assent Application Received |
Jan 24, 2025 | Administrative Review for Completeness |
Feb 07, 2025 | Bio Team Review for Completeness |
Feb 07, 2025 | Application Accepted |
Feb 07, 2025 | Project Manager |
Mar 17, 2025 | HPHC Historical Preservation No Effect |
Mar 18, 2025 | Biologist Report |
Mar 21, 2025 | Typist for Processing |
Mar 21, 2025 | Executive Sign Off |
Mar 21, 2025 | Permit Approved |
Mar 21, 2025 | Assent Correction Request Received |
Mar 26, 2025 | Permit Mailed |