Action Date | Action Description |
---|---|
Land Evidence Date | |
Mar 04, 2025 | Assent Application Received |
Mar 04, 2025 | Administrative Review for Completeness |
Mar 04, 2025 | Eng Team Review for Completeness |
Mar 04, 2025 | Project Manager |
Mar 04, 2025 | Application Accepted |
Mar 10, 2025 | Engineering Report |
Mar 10, 2025 | Correspondence Received |
Mar 24, 2025 | HPHC Historical Preservation No Effect |
Mar 28, 2025 | Executive Sign Off |
Mar 28, 2025 | Sent to Photo Copy |
Mar 28, 2025 | Permit Approved |
Mar 28, 2025 | Typist for Processing |
Apr 01, 2025 | Permit Mailed |