Action Date | Action Description |
---|---|
Mar 03, 2025 | Assent Application Received |
Mar 06, 2025 | Administrative Review for Completeness |
Mar 11, 2025 | Eng Team Review for Completeness |
Mar 11, 2025 | Bio Team Review for Completeness |
Mar 11, 2025 | Application Accepted |
Mar 11, 2025 | Project Manager |
Mar 18, 2025 | Engineering Report |
Mar 26, 2025 | Typist for Processing |
Mar 27, 2025 | Executive Sign Off |
Mar 27, 2025 | Permit Approved |
Mar 27, 2025 | Permit Mailed |
Mar 31, 2025 | HPHC Historical Preservation No Effect |