Action Date | Action Description |
---|---|
HPHC Review Pending | |
Eng Team Review for Completeness | |
Bio Team Review for Completeness | |
Project Manager | |
Nov 30, 2023 | Assent Application Received |
Dec 01, 2023 | Administrative Review for Completeness |
Dec 11, 2023 | Bio Team Review for Completeness |
Dec 11, 2023 | Application Accepted |
Dec 11, 2023 | Project Manager |
Dec 12, 2023 | Plans Received |
Jan 26, 2024 | Plans Received |
Feb 16, 2024 | Plans Received |
Feb 20, 2024 | HPHC Historical Preservation No Effect |
Feb 20, 2024 | Typist for Processing |
Feb 20, 2024 | Executive Sign Off |
Feb 20, 2024 | Sent to Photo Copy |
Feb 20, 2024 | Permit Approved |
Feb 20, 2024 | Biologist Report |
Feb 22, 2024 | Permit Mailed |
Mar 01, 2024 | Land Evidence Date |
Mar 18, 2024 | Commencement of Work Notice received |
Apr 07, 2025 | Modification Request |
Apr 10, 2025 | Administrative Review for Completeness |