Action Date | Action Description |
---|---|
Jan 22, 2025 | Assent Application Received |
Jan 28, 2025 | Administrative Review for Completeness |
Jan 31, 2025 | Bio Team Review for Completeness |
Jan 31, 2025 | Project Manager |
Jan 31, 2025 | Application Accepted |
Feb 25, 2025 | HPHC Historical Preservation No Effect |
Mar 04, 2025 | 30 day Public Notice Issued |
Mar 26, 2025 | Dock Meeting -- Approval |
Apr 04, 2025 | Public Notice End Date |
Apr 09, 2025 | Biologist Report |
Apr 14, 2025 | Typist for Processing |
Apr 14, 2025 | Executive Sign Off |
Apr 14, 2025 | Sent to Photo Copy |
Apr 14, 2025 | Permit Approved |
Apr 15, 2025 | Permit Mailed |
Apr 21, 2025 | Land Evidence Date |