Action Date | Action Description |
---|---|
Land Evidence Date | |
Feb 21, 2025 | Freshwater Wetlands Application - New - received |
Feb 26, 2025 | Administrative Review for Completeness |
Mar 05, 2025 | Additional Information Received |
Mar 10, 2025 | Application Accepted |
Mar 10, 2025 | Bio Team Review for Completeness |
Mar 10, 2025 | Project Manager |
Mar 31, 2025 | Additional Information Requested from Applicant |
Apr 08, 2025 | Biologist Report |
Apr 10, 2025 | HPHC Historical Preservation No Effect |
Apr 14, 2025 | Executive Sign Off |
Apr 14, 2025 | Sent to Photo Copy |
Apr 14, 2025 | Permit Approved |
Apr 14, 2025 | Typist for Processing |
Apr 16, 2025 | Permit Mailed |