Action Date | Action Description |
---|---|
Monitoring Report | |
Jan 29, 2025 | Assent Application Received |
Feb 03, 2025 | Administrative Review for Completeness |
Feb 12, 2025 | Bio Team Review for Completeness |
Feb 12, 2025 | Project Manager |
Feb 12, 2025 | Application Accepted |
Feb 25, 2025 | HPHC Historical Preservation No Effect |
Apr 21, 2025 | US Army Corps of Engineers Approval Received |
Apr 21, 2025 | Water Quality Certification |
Apr 22, 2025 | Biologist Report |
Apr 24, 2025 | Typist for Processing |
Apr 24, 2025 | Executive Sign Off |
Apr 24, 2025 | Sent to Photo Copy |
Apr 24, 2025 | Permit Approved |
Apr 29, 2025 | Permit Mailed |