Action Date | Action Description |
---|---|
Executive Sign Off | |
Sent to Photo Copy | |
Jan 30, 2025 | Assent Application Received |
Feb 03, 2025 | Administrative Review for Completeness |
Feb 26, 2025 | Bio Team Review for Completeness |
Feb 26, 2025 | Project Manager |
Feb 26, 2025 | Application Accepted |
Mar 17, 2025 | Additional Information Requested from Applicant |
Apr 29, 2025 | HPHC Historical Preservation No Effect |
May 02, 2025 | Additional Information Received |
May 14, 2025 | Biologist Report |
May 15, 2025 | Typist for Processing |