Action Date | Action Description |
---|---|
Land Evidence Date | |
Mar 06, 2025 | Maintenance Certification Request |
Mar 12, 2025 | Administrative Review for Completeness |
Mar 26, 2025 | Eng Team Review for Completeness |
Mar 26, 2025 | Project Manager |
Mar 26, 2025 | Application Accepted |
Apr 30, 2025 | HPHC Historical Preservation No Effect |
Jun 20, 2025 | Engineering Report |
Jun 23, 2025 | Typist for Processing |
Jun 23, 2025 | Executive Sign Off |
Jun 23, 2025 | Sent to Photo Copy |
Jun 23, 2025 | Permit Approved |
Jul 02, 2025 | Permit Mailed |