Action Date | Action Description |
---|---|
May 07, 2025 | Assent Application Received |
May 07, 2025 | Administrative Review for Completeness |
May 07, 2025 | CHA Worksheet received |
May 12, 2025 | Eng Team Review for Completeness |
May 12, 2025 | Project Manager |
May 12, 2025 | Application Accepted |
Jun 04, 2025 | US Army Corps of Engineers Project Number received. |
Jun 04, 2025 | 30 day Public Notice Issued |
Jun 13, 2025 | HPHC Historical Preservation No Effect |
Jul 04, 2025 | Public Notice End Date |
Jul 09, 2025 | Supervisor Engineer SignOff |
Jul 09, 2025 | Supervisor Biologist SignOff |
Jul 09, 2025 | Engineering Report |
Jul 10, 2025 | Executive Signoff of Staff Reports |
Jul 10, 2025 | Mail Agenda Notice |
Jul 22, 2025 | Semi-Monthly Meeting Date Scheduled |