Action Date | Action Description |
---|---|
Apr 18, 2025 | Freshwater Wetlands Application - New - received |
Apr 25, 2025 | Administrative Review for Completeness |
May 08, 2025 | Eng Team Review for Completeness |
May 08, 2025 | Bio Team Review for Completeness |
May 08, 2025 | Project Manager |
May 08, 2025 | Application Accepted |
Jun 13, 2025 | HPHC Historical Preservation No Effect |
Jul 01, 2025 | Biologist Report |
Aug 05, 2025 | Engineering Report |
Aug 06, 2025 | Typist for Processing |
Aug 06, 2025 | Executive Sign Off |
Aug 06, 2025 | Sent to Photo Copy |
Aug 06, 2025 | Permit Approved |
Aug 13, 2025 | Permit Mailed |