Action Date | Action Description |
---|---|
Land Evidence Date | |
Apr 17, 2025 | Assent Application Received |
Apr 17, 2025 | CHA Worksheet received |
Apr 23, 2025 | Administrative Review for Completeness |
May 13, 2025 | Additional Information Received |
May 15, 2025 | Additional Information Requested from Applicant |
Jun 23, 2025 | Additional Information Received |
Jul 02, 2025 | Correspondence Received |
Jul 03, 2025 | Application Accepted |
Jul 03, 2025 | Project Manager |
Jul 03, 2025 | Bio Team Review for Completeness |
Jul 22, 2025 | Correspondence Received |
Jul 24, 2025 | 15 day Public Notice Issued |
Aug 07, 2025 | US Army Corps of Engineers Project Number received. |
Aug 08, 2025 | Public Notice End Date |
Aug 12, 2025 | Engineering Report |
Aug 18, 2025 | HPHC Historical Preservation No Effect |
Aug 19, 2025 | Typist for Processing |
Aug 19, 2025 | Executive Sign Off |
Aug 19, 2025 | Sent to Photo Copy |
Aug 19, 2025 | Permit Approved |
Aug 21, 2025 | Permit Mailed |