| Action Date | Action Description |
|---|---|
| Engineering Report | |
| Nov 25, 2024 | Assent Application Received |
| Nov 26, 2024 | Administrative Review for Completeness |
| Dec 12, 2024 | Eng Team Review for Completeness |
| Dec 12, 2024 | Deficient Application - Owner Notification Sent |
| Jan 06, 2025 | Deficiency Response Received |
| Jan 27, 2025 | Eng Team Review for Completeness |
| Jan 27, 2025 | Application Accepted |
| Jan 27, 2025 | Project Manager |
| Jan 27, 2025 | Application Accepted |
| Feb 07, 2025 | HPHC Historical Preservation No Effect |
| Feb 21, 2025 | Additional Information Requested from Applicant |
| Jun 25, 2025 | Plans Received |
| Jul 24, 2025 | 30 day Public Notice Issued |
| Aug 07, 2025 | US Army Corps of Engineers Project Number received. |
| Aug 24, 2025 | Public Notice End Date |