| Action Date | Action Description |
|---|---|
| Executive Sign Off | |
| Sent to Photo Copy | |
| May 01, 2025 | Assent Application Received |
| May 06, 2025 | Administrative Review for Completeness |
| Jun 02, 2025 | Eng Team Review for Completeness |
| Jun 02, 2025 | Team Review for Completeness |
| Jun 02, 2025 | Application Accepted |
| Jun 02, 2025 | Category M assigned |
| Jun 24, 2025 | HPHC Historical Preservation No Effect |
| Aug 26, 2025 | Additional Information Requested from Applicant |
| Aug 26, 2025 | Plans Received |
| Sep 02, 2025 | Typist for Processing |
| Sep 02, 2025 | Engineering Report |
| Sep 02, 2025 | Geologist Report |
| Sep 02, 2025 | Correspondence Received |
| Sep 05, 2025 | Permit Mailed |