Action Date | Action Description |
---|---|
Legal Response/Decision | |
CHA -- application modified due to CHA info | |
Mar 26, 2025 | CHA Worksheet received |
Mar 26, 2025 | Assent Application Received |
Apr 01, 2025 | Administrative Review for Completeness |
Apr 09, 2025 | Eng Team Review for Completeness |
Apr 09, 2025 | Project Manager |
Apr 09, 2025 | Application Accepted |
Apr 28, 2025 | 30 day Public Notice Issued |
May 02, 2025 | HPHC Historical Preservation No Effect |
May 28, 2025 | Public Notice End Date |
Jun 04, 2025 | Engineering Report |
Jun 10, 2025 | Supervisor Engineer SignOff |
Jun 10, 2025 | Supervisor Biologist SignOff |
Jun 11, 2025 | Executive Signoff of Staff Reports |
Jun 23, 2025 | Mail Agenda Notice |
Jul 22, 2025 | Council Approval Granted |
Jul 22, 2025 | Semi-Monthly Meeting Date Scheduled |
Sep 09, 2025 | Stipulation Package by Engineer |