Action Date | Action Description |
---|---|
Land Evidence Date | |
Mar 26, 2025 | Assent Application Received |
Mar 26, 2025 | CHA Worksheet received |
Apr 01, 2025 | Administrative Review for Completeness |
Apr 07, 2025 | Bio Team Review for Completeness |
Apr 07, 2025 | Project Manager |
Apr 07, 2025 | Application Accepted |
Apr 15, 2025 | Objections/Comments Received |
Apr 15, 2025 | Entry of Appearance Received |
Apr 16, 2025 | Objections/Comments Received |
Apr 21, 2025 | Entry of Appearance Received |
Apr 21, 2025 | Objections/Comments Received |
May 27, 2025 | Additional Information Requested from Applicant |
May 28, 2025 | HPHC Historical Preservation No Effect |
Jun 24, 2025 | Additional Information Received |
Jul 24, 2025 | Objection withdrawal received |
Sep 02, 2025 | Correspondence Mailed/Faxed/E-mailed |
Sep 03, 2025 | Biologist Report |
Sep 09, 2025 | Typist for Processing |
Sep 09, 2025 | Executive Sign Off |
Sep 09, 2025 | Sent to Photo Copy |
Sep 09, 2025 | Permit Approved |
Sep 09, 2025 | Dock Post-Construction Certification by Engineer Required. |
Sep 10, 2025 | Permit Mailed |