Action Date | Action Description |
---|---|
Land Evidence Date | |
Jun 14, 2024 | Maintenance Certification Request |
Jun 21, 2024 | Administrative Review for Completeness |
Jul 02, 2024 | Eng Team Review for Completeness |
Jul 02, 2024 | Deficient Application - Owner Notification Sent |
Jul 22, 2024 | Deficiency Response Received |
Jun 30, 2025 | Additional Information Received |
Aug 29, 2025 | Application Accepted |
Aug 29, 2025 | Project Manager |
Aug 29, 2025 | Engineering Report |
Aug 29, 2025 | Eng Team Review for Completeness |
Sep 18, 2025 | HPHC Historical Preservation No Effect |
Sep 19, 2025 | Executive Sign Off |
Sep 19, 2025 | Sent to Photo Copy |
Sep 19, 2025 | Permit Approved |
Sep 19, 2025 | Dock Post-Construction Certification by Engineer Required. |
Sep 19, 2025 | Typist for Processing |
Sep 23, 2025 | Permit Mailed |