Action Date | Action Description |
---|---|
Land Evidence Date | |
Nov 25, 2024 | Assent Application Received |
Nov 26, 2024 | Administrative Review for Completeness |
Dec 12, 2024 | Eng Team Review for Completeness |
Dec 12, 2024 | Deficient Application - Owner Notification Sent |
Jan 06, 2025 | Deficiency Response Received |
Jan 27, 2025 | Eng Team Review for Completeness |
Jan 27, 2025 | Application Accepted |
Jan 27, 2025 | Project Manager |
Jan 27, 2025 | Application Accepted |
Feb 07, 2025 | HPHC Historical Preservation No Effect |
Feb 21, 2025 | Additional Information Requested from Applicant |
Jun 25, 2025 | Plans Received |
Jul 24, 2025 | 30 day Public Notice Issued |
Aug 07, 2025 | US Army Corps of Engineers Project Number received. |
Aug 24, 2025 | Public Notice End Date |
Sep 17, 2025 | Objections/Comments Received |
Sep 29, 2025 | Typist for Processing |
Sep 29, 2025 | Executive Sign Off |
Sep 29, 2025 | Sent to Photo Copy |
Sep 29, 2025 | Permit Approved |
Sep 29, 2025 | Engineering Report |
Sep 29, 2025 | Dock Post-Construction Certification by Engineer Required. |
Oct 01, 2025 | Permit Mailed |