Action Date | Action Description |
---|---|
Jul 03, 2025 | CHA Worksheet received |
Jul 03, 2025 | Assent Application Received |
Jul 08, 2025 | Administrative Review for Completeness |
Jul 09, 2025 | Bio Team Review for Completeness |
Jul 09, 2025 | Project Manager |
Jul 09, 2025 | Application Accepted |
Aug 20, 2025 | HPHC Historical Preservation Comments/Concerns |
Sep 11, 2025 | Additional Information Received |
Sep 16, 2025 | Biologist Report |
Sep 16, 2025 | Additional Information Received |
Sep 19, 2025 | Dock Post-Construction Certification by Engineer Required. |
Sep 19, 2025 | Typist for Processing |
Sep 19, 2025 | Executive Sign Off |
Sep 19, 2025 | Sent to Photo Copy |
Sep 19, 2025 | Permit Approved |
Sep 23, 2025 | Permit Mailed |
Oct 02, 2025 | Land Evidence Date |