Action Date | Action Description |
---|---|
Jul 14, 2025 | Freshwater Wetlands Application - New - received |
Jul 18, 2025 | Administrative Review for Completeness |
Aug 14, 2025 | Bio Team Review for Completeness |
Aug 14, 2025 | Project Manager |
Aug 14, 2025 | Application Accepted |
Sep 05, 2025 | HPHC Historical Preservation No Effect |
Sep 29, 2025 | Biologist Report |
Sep 30, 2025 | Typist for Processing |
Sep 30, 2025 | Executive Sign Off |
Sep 30, 2025 | Sent to Photo Copy |
Sep 30, 2025 | Permit Approved |
Sep 30, 2025 | Dock Post-Construction Certification by Engineer Required. |
Oct 01, 2025 | Permit Mailed |