| Action Date | Action Description |
|---|---|
| May 08, 2003 | Application Accepted |
| May 14, 2003 | 30 day Public Notice Issued |
| May 16, 2003 | Historical Preservation Approval Granted |
| May 23, 2003 | Objections/Comments Received |
| Sep 09, 2003 | 30-Day Notification of Cancellation letter |
| Sep 09, 2003 | Additional Information Requested from Applicant |
| Dec 31, 2003 | Correspondence Received |
| Feb 26, 2004 | Plans Received |
| Feb 23, 2005 | Plans Received |
| Mar 01, 2005 | 30 day Public Notice Issued |
| Mar 15, 2005 | Plans Received |
| Mar 17, 2005 | Correspondence Received |
| Mar 30, 2005 | Public Notice End Date |
| Apr 11, 2005 | Correspondence Received |
| Apr 26, 2005 | Plans Received |
| Apr 26, 2005 | US Army Corp of Engineers Permit Date |
| Apr 28, 2005 | US Army Corps of Engineers Approval Received |
| Apr 29, 2005 | Dock Subcommittee Meeting Held |
| May 18, 2005 | US Army Corps of Engineers Approval Received |
| May 20, 2005 | Correspondence Received |
| May 25, 2005 | Category A* (Docks) |
| May 26, 2005 | Typist for Processing |
| May 26, 2005 | Executive Sign Off |
| May 26, 2005 | Sent to Photo Copy |
| May 26, 2005 | Permit Approved |
| May 31, 2005 | Dock sub-committee Approved |
| Jun 06, 2005 | Land Evidence Date |