| Action Date | Action Description |
|---|---|
| Aug 29, 2011 | Assent Application Received |
| Aug 31, 2011 | Administrative Review for Completeness |
| Sep 01, 2011 | Team Review for Completeness |
| Sep 01, 2011 | Team Review for Completeness |
| Sep 01, 2011 | Application Accepted |
| Sep 14, 2011 | HPHC Historical Preservation No Effect |
| Oct 04, 2011 | 30 day Public Notice Issued |
| Nov 04, 2011 | Public Notice End Date |
| Nov 29, 2011 | Engineering Report |
| Dec 05, 2011 | Category A* (Docks) |
| Dec 05, 2011 | Biologist Report |
| Dec 06, 2011 | Typist for Processing |
| Dec 06, 2011 | Permit Approved |
| Dec 08, 2011 | Executive Sign Off |
| Dec 08, 2011 | Sent to Photo Copy |
| Dec 22, 2011 | US Army Corps of Engineers Approval Received |
| Jan 09, 2012 | Land Evidence Date |
| Mar 29, 2012 | Assent Correction Mailed |
| May 07, 2012 | Commencement of Work Notice received |