| Action Date | Action Description |
|---|---|
| Feb 28, 2017 | Assent Application Received |
| Feb 28, 2017 | Administrative Review for Completeness |
| Mar 01, 2017 | Team Review for Completeness |
| Mar 01, 2017 | Application Accepted |
| Mar 22, 2017 | Engineering Report |
| Mar 23, 2017 | Typist for Processing |
| Mar 23, 2017 | Executive Sign Off |
| Mar 23, 2017 | Sent to Photo Copy |
| Mar 23, 2017 | Permit Approved |
| Apr 05, 2017 | HPHC Historical Preservation No Effect |