| Action Date | Action Description |
|---|---|
| Mar 22, 2017 | Assent Application Received |
| Mar 22, 2017 | Administrative Review for Completeness |
| Mar 24, 2017 | Team Review for Completeness |
| Mar 24, 2017 | Team Review for Completeness |
| Mar 24, 2017 | Application Accepted |
| Mar 24, 2017 | Category A* (Docks) |
| Apr 06, 2017 | 30 day Public Notice Issued |
| Apr 10, 2017 | HPHC Historical Preservation No Effect |
| Apr 28, 2017 | Correspondence Mailed/Faxed/E-mailed |
| May 06, 2017 | Public Notice End Date |
| May 20, 2017 | Public Notice End Date Extension Granted |
| May 22, 2017 | Objections/Comments Received |
| May 31, 2017 | Meeting Held |
| Jul 27, 2017 | Additional Information Received |
| Jul 28, 2017 | Plans Received |
| Nov 22, 2017 | Typist for Processing |
| Nov 22, 2017 | Executive Sign Off |
| Nov 22, 2017 | Sent to Photo Copy |
| Nov 22, 2017 | Permit Approved |
| Nov 22, 2017 | Biologist Report |
| Nov 22, 2017 | Engineering Report |
| Nov 30, 2017 | Land Evidence Date |
| Mar 18, 2024 | Dock Post-Construction Certification by Engineer received. |