| Action Date | Action Description |
|---|---|
| Mar 05, 2020 | Assent Application Received |
| Mar 06, 2020 | Administrative Review for Completeness |
| Mar 06, 2020 | Bio Team Review for Completeness |
| Mar 06, 2020 | Project Manager |
| Mar 06, 2020 | Application Accepted |
| Mar 31, 2020 | Additional Information Received |
| Mar 31, 2020 | Additional Information Requested from Applicant |
| Apr 02, 2020 | HPHC Historical Preservation Comments/Concerns |
| Apr 07, 2020 | Correspondence Received |
| Apr 07, 2020 | Additional Information Received |
| May 04, 2020 | HPHC Historical Preservation Comments/Concerns |
| May 05, 2020 | Correspondence Received |
| May 06, 2020 | HPHC Historical Preservation No Effect |
| May 06, 2020 | HPHC Review Pending |
| May 20, 2020 | Biologist Report |
| May 21, 2020 | Typist for Processing |
| May 21, 2020 | Executive Sign Off |
| May 21, 2020 | Sent to Photo Copy |
| May 21, 2020 | Permit Approved |
| May 28, 2020 | Land Evidence Date |