| Action Date | Action Description |
|---|---|
| Legal Response/Decision | |
| Mar 02, 2021 | CHA Worksheet received |
| Mar 02, 2021 | Assent Application Received |
| Mar 02, 2021 | Administrative Review for Completeness |
| Mar 10, 2021 | Bio Team Review for Completeness |
| Mar 10, 2021 | Application Accepted |
| Mar 10, 2021 | Project Manager |
| Mar 16, 2021 | HPHC Review Pending |
| Mar 16, 2021 | HPHC Historical Preservation No Effect |
| Apr 27, 2021 | Letter of Support for Project |
| Apr 28, 2021 | Letter of Support for Project |
| Apr 30, 2021 | Comments Received |
| May 03, 2021 | Letter of Support for Project |
| May 03, 2021 | Letter of Support for Project |
| May 03, 2021 | Letter of Support for Project |
| May 03, 2021 | Letter of Support for Project |
| May 10, 2021 | Letter of Support for Project |
| May 10, 2021 | Letter of Support for Project |
| May 10, 2021 | Letter of Support for Project |
| May 10, 2021 | Letter of Support for Project |
| May 12, 2021 | Letter of Support for Project |
| May 12, 2021 | Letter of Support for Project |
| May 12, 2021 | Letter of Support for Project |
| May 17, 2021 | Letter of Support for Project |
| May 17, 2021 | Letter of Support for Project |
| May 18, 2021 | Letter of Support for Project |
| May 19, 2021 | Letter of Support for Project |
| May 21, 2021 | Letter of Support for Project |
| May 24, 2021 | Letter of Support for Project |
| May 25, 2021 | 30 day Public Notice Issued |
| Jun 09, 2021 | Correspondence Received |
| Jun 14, 2021 | Letter of Support for Project |
| Jun 25, 2021 | Public Notice End Date |
| Jul 19, 2021 | Plans Received |
| Aug 04, 2021 | Water Quality Certification |
| Aug 10, 2021 | Public Hearing Notices Mailed |
| Sep 02, 2021 | Biologist Report |
| Sep 02, 2021 | Engineering Report |
| Sep 03, 2021 | Semi-Monthly Meeting Postponed |
| Sep 10, 2021 | Letter of Support for Project |
| Sep 28, 2021 | Semi-Monthly Meeting Date Scheduled |
| Oct 05, 2021 | Mail Agenda Notice |
| Oct 12, 2021 | Semi-Monthly Meeting Date Scheduled |
| Oct 19, 2021 | Semi-Monthly Meeting Date Scheduled |
| Oct 19, 2021 | Council Approval Granted |
| Oct 22, 2021 | Stipulation Package from Biologist |
| Nov 01, 2021 | Stipulation Package by Engineer |
| Nov 16, 2021 | Typist for Processing |
| Nov 16, 2021 | Executive Sign Off |
| Nov 16, 2021 | Sent to Photo Copy |
| Nov 16, 2021 | Permit Approved |
| Nov 18, 2021 | Permit Mailed |
| Sep 12, 2024 | Extension of Permit Request |
| Jan 07, 2025 | Enforcement Compliance Inspection Required |
| Jan 14, 2025 | Process Extension |
| Jan 14, 2025 | Extension Approved |